Owner experience · privacy level 1

Rashid, here is the project today.

Full visibility across the entire project and portfolio.

Ask IMARAH

Progress

41.5%

Day 148 of 388

Health score

86/100

Execution — Superstructure

Programme

+9 days

Projected completion 2027-02-13

Submission risk

62/100

214 rules checked — risk flags, not approval

Commercial position

AED 4.68M

Measured works (BOQ)

AED 3.19M

Spent to date

AED 8.7M

Projected final

Your tasks today

1

  • T-1049 Review and approve variation VO-004 cost impact
Open task engine →

IMARAH risk prediction

82%

12 day delay risk on the facade package

Gulf Facade Systems delivered late on 3 of their last 4 projects on IMARAH, and the 12-week manufacturing lead time now overlaps the summer productivity buffer.

Release the porcelain panel order 10 days earlier than programmed.

64%

MEP sleeve block consumes remaining float in 2 days

ME-100 Rev B has been outstanding for 4 days. Slab pour cannot proceed without sleeve positions confirmed.

Escalate to the design lead today; the task already sits on the critical path.

41%

Compliance resubmission may extend by 6 days

Two open findings (CMP-01 rear setback, CMP-02 plot coverage) require coordinated drawing revisions before submission.

Resolve both in one revision cycle rather than sequentially.

What this role can and cannot see

  • Every financial figure
  • All contractor rates
  • Complete audit log
  • Risk and escalation queue
  • No restrictions at this level.