Daily tasks · Day 148
Good morning, Rashid. Your tasks for today.
IMARAH assigns work each morning from the programme, and collects what actually happened each evening — in the language each person works in.
Tasks today
1
0 already complete
Completion
0%
End of day target 100%
Blocked
1
Reason required by IMARAH
Man hours
1
Planned across assigned teams
Not startedT-1049Commercial
Review and approve variation VO-004 cost impact
Rashid Al Maktoum · 1h · coordinate with Mariam Al Suwaidi
Materials today
- Delivered
Ready-mix concrete C40
62 m³ · Unibeton · ETA 06:30
- Delivered
High-yield rebar T16 / T20
4.2 ton · Emirates Steel · ETA 09:00
- In transit
Formwork panels, replacement set
120 m² · Doka Gulf · ETA 14:00
- On hold — drawing revision
MEP sleeves and inserts
1 lot · Zenith MEP · ETA Hold
Submit end of day
Anything not completed needs a reason. That reason is what lets IMARAH attribute delay honestly instead of guessing.