Daily tasks · Day 148

Good morning, Rashid. Your tasks for today.

IMARAH assigns work each morning from the programme, and collects what actually happened each evening — in the language each person works in.

Tasks today

1

0 already complete

Completion

0%

End of day target 100%

Blocked

1

Reason required by IMARAH

Man hours

1

Planned across assigned teams

Not startedT-1049Commercial

Review and approve variation VO-004 cost impact

Rashid Al Maktoum · 1h · coordinate with Mariam Al Suwaidi

Materials today

  • Ready-mix concrete C40

    62 m³ · Unibeton · ETA 06:30

    Delivered
  • High-yield rebar T16 / T20

    4.2 ton · Emirates Steel · ETA 09:00

    Delivered
  • Formwork panels, replacement set

    120 m² · Doka Gulf · ETA 14:00

    In transit
  • MEP sleeves and inserts

    1 lot · Zenith MEP · ETA Hold

    On hold — drawing revision

Submit end of day