Reports & project history

Ask for day 15 on day 148. It is still there.

Every day of the project is stored, attributed and replayable — with photos, blockers and the reason behind every one.

Week 22

Progress this week

2.8%

Planned 3.4%

Spend this week

AED 187.4K

Certified and committed

Schedule

9 days behind

9 days behind original programme, 5 days recoverable

Risk outlook

Medium

Zero lost-time incidents. Safety score 94 / 100.

Day 148 · 8 June 2026

Slab reinforcement advancing, sleeve coordination still blocked

Progress at this date

41.5%

Completed

  • Slab formwork grid 4–7 signed off by site engineer
  • Pre-pour survey and level check, zone B
  • Toolbox talk — working at height
  • Weekly progress package issued to client

In progress

  • Slab reinforcement fixing, zone C
  • Porcelain panel order release with Gulf Facade Systems
  • Revised rear setback plan for municipality resubmission

Not completed

  • MEP sleeve coordination

    ME-100 Rev B still outstanding. Escalated to the design team — 2 day float remaining before it hits the critical path.

  • CMP-03 travel distance resolution

    Awaiting Civil Defence consultant input on the secondary stair option.

progress
Slab reinforcement fixing, zone C
quality
Level check in progress, zone B
progress
Material laydown area, rebar delivery

Safety: Zero incidents. 41 days without a lost-time incident.

Materials: Ready-mix C40 — 62 m³ received · Rebar T16/T20 — 4.2 ton received · Formwork panels — in transit, 14:00

Critical issues this week

  • ME-100 Rev B outstanding — blocks the slab pour sequence
  • Rear setback finding CMP-01 must clear before resubmission

Audit trail

Append-only. Day 148 and backwards.

  • Pre-pour survey signed off, zone B

    Day 148 · 08:12 · Ahmed Farouk

  • MEP sleeve block escalated to design team — float at 2 days

    Day 148 · 07:40 · IMARAH Intelligence

  • Daily report submitted and distributed to 6 stakeholders

    Day 147 · 17:55 · Vinod Kumar

  • Contact request from contractor for client number — declined, routed to PM

    Day 147 · 14:22 · IMARAH Intelligence

  • Variation VO-004 raised automatically from compliance finding CMP-04

    Day 146 · 11:05 · IMARAH Intelligence

  • AR-100 Rev D uploaded — profile re-parsed, 2 findings updated

    Day 145 · 09:31 · Youssef Haddad