AI Timeline

A programme that understands approvals, summer and Ramadan.

Built from the same intelligence, and recalculated the moment reality moves.

9 days net slip

Today

Day 148

of 388 programmed days

Progress

41.5%

Execution — Superstructure

Original completion

2027-02-04

Contract date

Projected completion

2027-02-13

9 days later than contract

Programme

Critical pathNon-critical

Concept & schematic design

Arqyon Architecture

Detailed design & documentation

Arqyon Architecture

Municipality submission & NOCs

Arqyon Architecture

Enabling works & excavation

Emirates Build

Foundations & tie beams

Emirates Build

Superstructure — columns & slabs

Emirates Build

Blockwork & plaster

Emirates Build

Waterproofing & roofing

Emirates Build

Facade & glazing

Gulf Facade Systems

MEP first & second fix

Zenith MEP

Internal finishes & joinery

Emirates Build

External works & landscaping

Verde Landscapes

Testing, commissioning & snagging

Zenith MEP

Completion certificate & handover

Arqyon Construction

Conditions modelled into the programme

  • Municipality approval window

    Historic DM/DSDA average for G+1 villas: 23 working days

  • Dubai summer productivity buffer

    Midday break regulation, June 15 – September 15. Output modelled at 78%.

  • Ramadan working-hour adjustment

    Reduced shift length. Programme absorbs 6 days automatically.

  • Facade material lead time

    Porcelain panel manufacture and shipping — 12 weeks ex-Italy

Milestones

  • Building permit issuedDay 106Done
  • Foundations completeDay 146Done
  • Superstructure topped outDay 204Planned
  • Building watertightDay 294Planned
  • Practical completionDay 376Planned

Why the project moved

Every day of slip is attributed, and IMARAH records how much the programme absorbed.

Precast stair supplier delivered 9 days late

9d · 5d net

Attributed to Procurement

Rebar inspection re-scheduled by consultant

3d · 0d net

Attributed to Consultant

Client variation — kitchen specification change

12d · 4d net

Attributed to Client

Unseasonal rainfall, February

2d · 0d net

Attributed to Weather