A programme that understands approvals, summer and Ramadan.
Built from the same intelligence, and recalculated the moment reality moves.
Today
Day 148
of 388 programmed days
Progress
41.5%
Execution — Superstructure
Original completion
2027-02-04
Contract date
Projected completion
2027-02-13
9 days later than contract
Programme
Concept & schematic design
Arqyon Architecture
Detailed design & documentation
Arqyon Architecture
Municipality submission & NOCs
Arqyon Architecture
Enabling works & excavation
Emirates Build
Foundations & tie beams
Emirates Build
Superstructure — columns & slabs
Emirates Build
Blockwork & plaster
Emirates Build
Waterproofing & roofing
Emirates Build
Facade & glazing
Gulf Facade Systems
MEP first & second fix
Zenith MEP
Internal finishes & joinery
Emirates Build
External works & landscaping
Verde Landscapes
Testing, commissioning & snagging
Zenith MEP
Completion certificate & handover
Arqyon Construction
Conditions modelled into the programme
Municipality approval window
Historic DM/DSDA average for G+1 villas: 23 working days
Dubai summer productivity buffer
Midday break regulation, June 15 – September 15. Output modelled at 78%.
Ramadan working-hour adjustment
Reduced shift length. Programme absorbs 6 days automatically.
Facade material lead time
Porcelain panel manufacture and shipping — 12 weeks ex-Italy
Milestones
- Building permit issuedDay 106Done
- Foundations completeDay 146Done
- Superstructure topped outDay 204Planned
- Building watertightDay 294Planned
- Practical completionDay 376Planned
Why the project moved
Every day of slip is attributed, and IMARAH records how much the programme absorbed.
Precast stair supplier delivered 9 days late
9d · 5d net
Attributed to Procurement
Rebar inspection re-scheduled by consultant
3d · 0d net
Attributed to Consultant
Client variation — kitchen specification change
12d · 4d net
Attributed to Client
Unseasonal rainfall, February
2d · 0d net
Attributed to Weather