AI Compliance Review

Checked against Dubai Municipality and DSDA before submission.

IMARAH reads the drawing set against the rulebook and flags risk with a reference and a correction. It does not approve anything — your consultant still signs.

5 open findings

Rules checked

214

207 cleared

Submission risk

62%

Probability of a first-review rejection

Resubmission exposure

19 days

Historic DM / DSDA cycle

Authority

DM / DSDA

District 7, Dubai South, Dubai, UAE

Submission readiness

207/214
criticalArchitecturalCMP-01

Rear setback for G+1 villa plots

DM Building Regulations — Villa Setbacks, Cl. 3.2.4 (rear ≥ 3.0 m)

Detected
Rear setback measured at 2.4 m along grid E between axes 4–7 on AR-100 Rev D.
Risk
Submission likely rejected at first review. Historic resubmission cycle: 17–24 days.
Correction
Pull the rear wall line forward by 600 mm, or reduce the ground floor service block depth to 3.9 m.
highArchitecturalCMP-02

Maximum plot coverage

DSDA District 7 Development Control — Cl. 5.1 (max 60% ground coverage)

Detected
Ground coverage computed at 61.4% (645 m² over 1,050 m² plot).
Risk
Coverage overrun of 14.7 m². Commonly triggers a formal design revision request.
Correction
Reduce the covered terrace by 15 m², or reclassify it as an open shaded pergola per Cl. 5.1(b).
highFire & Life SafetyCMP-03

Travel distance to a protected exit

UAE Fire & Life Safety Code 2018 — Ch. 2, Table 2.3 (single exit ≤ 20 m)

Detected
First floor travel distance from Bedroom 4 to the stair core measures 23.1 m.
Risk
Civil Defence NOC delay. Typically a 2-week hold on approval.
Correction
Introduce a secondary protected stair, or relocate the Bedroom 4 door 3.4 m towards the core.
mediumSustainabilityCMP-04

Glazing thermal performance

Al Sa'fat Green Building — Silver, Cl. 4.2.1 (U ≤ 1.9 W/m²K, SHGC ≤ 0.32)

Detected
Specified double glazing at SHGC 0.36 on the west-facing family lounge.
Risk
Downgrade from Silver rating; cooling load rises approximately 6%.
Correction
Switch to a low-E double-glazed unit at SHGC 0.28 — cost delta AED 41,000.
mediumStructuralCMP-05Resolved

Minimum concrete cover in aggressive soil

DM Structural Guidelines — Cl. 7.4 (footings ≥ 75 mm cover)

Detected
ST-100 Rev B specifies 50 mm cover to pad footing reinforcement.
Risk
Durability non-conformance flagged during structural checking.
Correction
Increase cover to 75 mm and re-issue ST-100 with the revised bar schedule.
advisoryMEPCMP-06

Accessible plant clearance

DM MEP Guidelines — Cl. 9.6 (≥ 900 mm maintenance clearance)

Detected
Roof VRF condenser bank shows 780 mm clearance on the north side.
Risk
Maintenance access observation at inspection. Not a submission blocker.
Correction
Shift the condenser bank 150 mm south — no structural implication.
advisoryArchitecturalCMP-07Resolved

Parking provision

DSDA Parking Standards — Cl. 2.2 (2 covered bays per villa)

Detected
2 covered bays plus 1 visitor bay provided. Compliant.
Risk
None. Meets requirement with a surplus visitor bay.
Correction
No action required.