Rashid, here is the project today.
Full visibility across the entire project and portfolio.
Progress
41.5%
Day 148 of 388
Health score
86/100
Execution — Superstructure
Programme
+9 days
Projected completion 2027-02-13
Submission risk
62/100
214 rules checked — risk flags, not approval
Commercial position
AED 4.68M
Measured works (BOQ)
AED 3.19M
Spent to date
AED 8.7M
Projected final
IMARAH risk prediction
12 day delay risk on the facade package
Gulf Facade Systems delivered late on 3 of their last 4 projects on IMARAH, and the 12-week manufacturing lead time now overlaps the summer productivity buffer.
Release the porcelain panel order 10 days earlier than programmed.
MEP sleeve block consumes remaining float in 2 days
ME-100 Rev B has been outstanding for 4 days. Slab pour cannot proceed without sleeve positions confirmed.
Escalate to the design lead today; the task already sits on the critical path.
Compliance resubmission may extend by 6 days
Two open findings (CMP-01 rear setback, CMP-02 plot coverage) require coordinated drawing revisions before submission.
Resolve both in one revision cycle rather than sequentially.